Stock-outs and overstock usually have the same cause: reorders made from memory instead of a plan. Small brands rarely need complex software to fix this. They need one sheet that shows what's on hand, what's coming and how fast it's selling, and a habit of checking it before it's too late to act.
Know your days of cover
For each SKU, divide stock on hand by average daily sales. That's how many days you can keep selling before you run out. Use recent sales, such as the last four weeks, and adjust for promotions you know are coming. Count stock at every location, including a second 3PL or stock held by a supplier, and subtract what's already committed to open orders.
Get real lead times from suppliers
Lead time is the time from placing a PO to stock being available to sell, not the supplier's quoted production time. Include shipping, customs, receiving at the 3PL and any quality checks. Track actual lead times for each supplier and use those, not the optimistic number from the first email.
Set reorder points and order quantities
A reorder point is the stock level at which you place the next order: daily sales multiplied by lead time, plus a safety buffer. The order quantity should cover the next stretch of sales, often 60 to 90 days, less what's already on hand and inbound. Round to supplier minimums and case packs. When a SKU crosses its reorder point, it gets flagged.
Plan around seasonality and promotions
Average daily sales hide spikes. If you run a big sale every November or a launch every spring, plan stock for those weeks separately and order early enough to cover the longer lead times suppliers often have at busy times of year. Talk to marketing before a promotion is scheduled, not after, so a successful campaign doesn't end in a stock-out. For the big sale weekend itself, see getting ready for Black Friday.
Track components, not only finished goods
If you assemble products or kits, the finished SKU is only as available as its scarcest component. Bottles, labels, cartons and bulk ingredients each have their own suppliers and lead times. Keep a component list for each product and plan components with the same reorder logic. A missing label can stop a production run just as surely as a missing ingredient.
Follow up before things are late
Every open PO should have an expected date and an owner. Check in with suppliers a week or two before that date rather than after it passes. Note any quality checks needed on arrival. When a delay is confirmed, update the plan straight away and decide whether to expedite, substitute or slow down marketing on the affected product.
Watch for overstock too
Cash sitting in slow-moving stock is a leak as well. Flag SKUs with far more cover than they need and stop reordering them until they come down. Consider bundles or promotions to move them, and check whether storage fees at the 3PL are growing because of them.
Discontinued products need the same attention. When you retire a SKU, stop reordering its components, decide what to do with remaining stock, and remove it from subscriptions and bundles so it can't be sold after it's gone.
Make it a weekly routine
Update the sheet once a week from the store and 3PL, review flagged SKUs and open POs, and approve the orders that need placing. AI tools can do much of the data pulling and draft the POs; a person should approve every order before it goes to a supplier.
Where we come in
We build reorder planners and run procurement for small brands: supplier follow-up, component tracking, PO drafting and 3PL receiving. Every PO waits for the owner's OK. A free ops audit call is a good way to see where your stock planning stands.